CDM stands for the Construction (Design and Management) Regulations 2015, the regulations that govern health and safety on construction projects in Great Britain. HSE says they apply to all construction work, including domestic projects, and they set duties for clients, designers, principal designers, principal contractors, contractors and workers. For a tree or grounds firm the question is whether the job counts as construction work: clearing a plot so that a building can go up does, and a routine hedge cut in a park does not.

What CDM 2015 is

The Construction (Design and Management) Regulations 2015 came into force in Great Britain on 6 April 2015, and HSE’s pages shorten the name to CDM 2015. There is no small-project exemption: in its FAQ, HSE states that CDM 2015 applies to all construction work including domestic projects.

What counts as construction work

Regulation 2 defines construction work as the carrying out of any building, civil engineering or engineering construction work, and lists what that includes:

  • building, altering, fitting out, renovating, repairing, maintaining, demolishing or dismantling a structure;
  • “the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation (but not pre-construction archaeological investigations), and the clearance or preparation of the site or structure for use or occupation at its conclusion”;
  • assembling or disassembling prefabricated elements on site;
  • removing a structure, or the waste from demolition or dismantling;
  • installing, maintaining or removing mechanical, electrical, gas, telecommunications and similar services.

A contractor is any person, including a non-domestic client, who carries out, manages or controls construction work in the course of a business. The list of structures (buildings, railways, docks, bridges, pipelines, tunnels and towers among them) does not mention trees.

When CDM applies to tree and grounds work

Site clearance in preparation for an intended structure is construction work in its own right. A tree firm that fells, chips and grubs out a plot so that houses or a warehouse can be built is doing construction work in the course of a business, so it is a contractor with the duties below. Great Oaks does this kind of work as site clearance in Preston and across Lancashire, and there is a separate article on vegetation clearance before construction.

A hedge cut in a public park, a mowing round or a pruning visit to a finished housing estate is different. No structure is being built, altered, maintained or taken down, and nothing is being prepared for one, so on the definition as written it is hard to see which limb would apply. Neither the regulations nor the HSE pages we read say so in terms. HSE’s FAQ also gives a plain no to whether CDM 2015 applies to all maintenance work.

The regulations do not mention tree work, landscaping or grounds maintenance by name. Jobs in between, such as clearing scrub round a site compound, turn on the facts, so ask the client or the principal contractor before you price the job. Great Oaks Training offers a CDM awareness online course, an online awareness course taken on a phone, tablet or computer.

CDM awareness is one of five online awareness courses in our Supervisor Safety pack, for supervisors and team leaders who plan the work and look after a crew.

Who the duty holders are

HSE’s summary of duties names seven:

  • Commercial clients: make suitable arrangements for managing the project, appoint the other duty holders and provide welfare facilities.
  • Domestic clients: people having work done on their own home. Their duties normally pass to the contractor or principal contractor.
  • Designers: eliminate, reduce or control foreseeable risks during construction and in the use and maintenance of the building.
  • Principal designers: plan, manage, monitor and coordinate health and safety in the pre-construction phase.
  • Principal contractors: do the same in the construction phase, prepare the construction phase plan, give site inductions, prevent unauthorised access and provide welfare facilities.
  • Contractors: plan, manage and monitor construction work under their control so that it is carried out without risks to health and safety.
  • Workers: take care of themselves and others, report anything likely to endanger health and safety, cooperate with the other duty holders, and be consulted on matters that affect them.

Under regulation 5, where more than one contractor is, or is reasonably foreseeable to be, working on a project, the client must appoint a principal designer and a principal contractor in writing before the construction phase begins. If it does not, the client carries those duties itself.

What a contractor must do before starting on site

Regulation 15 sets out the contractor’s duties. For a tree or grounds firm arriving on a construction site they come to this:

  1. Check the client knows its duties. A contractor must not carry out construction work unless satisfied that the client is aware of the duties it owes under the regulations.
  2. Find out who the principal contractor is. Where more than one contractor is on the project, you must comply with any directions from the principal designer or principal contractor and with the parts of the construction phase plan that apply to your work.
  3. If you are the only contractor, the plan is yours. A sole contractor must take account of the general principles of prevention and draw up a construction phase plan, or arrange for one, as soon as is practicable. HSE’s page for contractors says before setting up the site.
  4. Put the right people on the job. You must not employ or appoint a person to work on a construction site unless they have, or are obtaining, the necessary skills, knowledge, training and experience for their tasks: for a clearance crew, chainsaw, chipper and climbing training that matches the plan.
  5. Supervise, instruct and inform. Each worker under your control must have appropriate supervision, instructions and information, including a site induction where the principal contractor has not already given one, and the procedures for serious and imminent danger.
  6. Keep the public out. A contractor must not begin work on a construction site unless reasonable steps have been taken to prevent access by unauthorised persons. For a crew felling and chipping beside a footpath or park, that would mean keeping passers-by out of the work area before the first cut.
  7. Welfare. A contractor must ensure, so far as is reasonably practicable, that the welfare requirements in Schedule 2 are met.

Under regulation 8, the firm itself, as a contractor appointed to a project, must have the skills, knowledge and experience and, if it is an organisation, the organisational capability to do its role safely, and must not accept the appointment unless it does.

When a project has to be notified to HSE

Notification is a separate duty, and it falls on the client. HSE’s wording is that a construction project is notifiable if the construction work is expected to last longer than 30 working days and have more than 20 workers working at the same time at any point on the project, or to exceed 500 person days. Regulation 6 requires the client to give notice in writing to HSE as soon as is practicable before the construction phase begins, and to display the notice in the site office where any worker can read it. HSE takes the notice through its online form F10 and no longer accepts paper, email or post. The thresholds decide whether HSE must be told, not whether CDM applies.

Frequently asked questions

What does CDM stand for in construction?

The Construction (Design and Management) Regulations 2015.

When do the CDM regulations apply?

Whenever construction work, as defined in regulation 2, is carried out, whatever the size of the job. HSE says this includes domestic projects.

What is CDM 2015 compared with CDM 2007?

HSE’s FAQ refers to the earlier regulations as CDM 2007 and says the definition of construction work did not change between them.

Does CDM apply to tree surgery?

It can. Clearing trees from a plot ahead of building is site clearance in preparation for an intended structure, which is construction work. Pruning, hedge cutting and mowing with no structure involved fall outside the definition on its ordinary reading, and HSE’s FAQ confirms that CDM 2015 does not apply to all maintenance work, but no HSE page says so for tree work in terms.

If your crews work on development sites or alongside other trades, the CDM awareness online course from Great Oaks Training is the one to look at. It is taken on a phone, tablet or computer, it checks knowledge and ends with a certificate of completion, and it does not replace the site induction or the practical, task-specific training your firm gives its people. It sits alongside the other online health and safety courses for tree, grounds and landscaping firms.